1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
Meeting called to order by Joseph Cermele.
Roll call conducted by Margaret Uhle:
Ms. Uhle: States Chairman DelSavio and JoAnn
7 Murphy will not be able to attend the meeting.
8 Mr. Cermele: States he will be chairing the
meeting tonight. Explains because there are
9 only three of the five board members applicants
will need a unanimous vote. States the
10 following applications have been adjourned:
Application 05-49, Walgreens; Application
11 05-43, Omnipoint Communications, 60 Glenn Road;
Application 05-99, 42 Orchard Street;
12 Application 05-88, 292 White Plains Road.
13 Ms. Uhle: States application for 29 Joyce Road
will be adjourned to the January 25th meeting.
Mr. Cermele: Explains since there are only
15 three of the five board members present each
applicant can adjourn their application for the
16 next meeting. States Application 05-74 is
present and wishes to proceed; Application
17 05-85 is present and wishes to proceed;
Application 05-89 is present and wishes to
18 proceed; Application 05-11 is present and
wishes to proceed. States representative for
19 Application 05-58 is not present yet. States
representative for Application 05-86 is
20 present. States Application 05-20 is present
and wishes to proceed. States representative
21 for Application 05-100 is not present yet.
APPLICATION 05-74, 24 GRAND BOULEVARD
24 Town Planner: States this is an application
for a new single family home. Explains they
25 appeared before the Planning Board at the
October 26th meeting and the Board asked that
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
the applicant provide additional information,
2 which is listed on the memo, most specifically
with regard to providing a clearer grading and
3 drainage plan, being clearer with regard to the
trees to remain and be removed, a tree
4 protection plan and redesigning of the driveway
that's proposed for the existing residence.
Mr. Cotugno: John Cotugno, architect for the
6 applicant. States he revised the plans to show
the new driveway at the existing home to be
7 located six feet away from the property line
whereas the original plans showed it three feet
8 away. States he changed the shape of the
driveway to make it more architectural. States
9 they show the existing trees and tree
protection both for the new house and the
10 driveway construction and they show it going
into an existing walkway. Shows evergreens and
11 lamp post around the driveway. Shows curtain
Mr. Cermele: Discusses driveway. Asks if
13 there is any edging for the driveway.
14 Mr. Cotugno: States yes, asphalt curb on both
Ms. Cascione: Asks if the existing garage on
16 the new lot has been demolished yet.
17 Mr. Cotugno: States no.
18 Mr. Cermele: Suggests a Belgian block or some
other type of edging other than asphalt.
Mr. Cotugno: States they will do it on both
20 houses. Feels it is a good enhancement.
21 Mr. Pulaski: States there are a lot of houses
along that road that have an apron on the
22 driveway. Feels that would improve it
particularly on the existing house.
Mr. Cotugno: Feels if they do the apron in the
24 cobblestone they should keep the rest blue
Ms. Uhle: States zoning law requires the
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
Mr. Cotugno: States he doesn't like the look
3 of the cobblestone with the blacktop.
4 Mr. Pulaski: Makes a motion to reopen the
public hearing on Application 05-74.
Ms. Cascione: Seconds motion.
Mr. Moses: Manfred Moses. Asks if any
8 variances are required for this application.
9 Ms. Uhle: States no variances are required.
10 Mr. Moses: Asks if it meets all the zoning
Ms. Uhle: States yes. Explains the existing
12 house does not meet one of the side yard
setbacks but that's an existing non-conforming
13 setback so that can remain. States the new
house meets all the current zoning
15 Ms. Cascione: Makes a motion to close the
public hearing on Application 05-74.
Mr. Pulaski: Seconds motion.
Mr. Pulaski: Feels what would really make this
19 application work is if both driveways had the
apron with the cobblestone.
Ms. Uhle: Reviews conditions: Any existing
21 structures to be demolished will be demolished
prior to obtaining the building permit for the
22 new construction; driveway for the existing
house will be constructed prior to obtaining
23 the permit for the new construction so that
that lot is fully conforming; both new
24 driveways will have belgian block curbs and
Mr. Pulaski: Makes a motion to approve
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
Application 05-74, 24 Grand Boulevard with the
2 conditions and recommendations stated by Ms.
Ms. Cascione: Seconds motion.
6 APPLICATION 05-85, 10 GREYSTONE CIRCLE
Ms. Uhle: Explains this is an application for
8 additions and alterations and a second story
addition to an existing single family
9 residence. States application appeared before
this Board at the October 26th meeting after it
10 had already been reviewed by the ARB and there
was confusion at the last meeting because the
11 applicant had made some changes to what the ARB
approved and this Board asked the applicant to
12 provide everything on one set of drawings and
reference everything back to the plans dated
14 Mr. Adley: John Adley, professional engineer
representing the applicant. States Planning
15 Board requested changes since the last meeting.
States they have made the changes and submitted
16 them to the Board. Explains they changed the
columns to a ten inch column and the entrance
17 door has two side lights on either side of the
door. States they changed the door on the
18 second level to a French door. States they
kept the windows in the front the same size in
19 width but increased the height. States they
added the brick soldier course at the back and
20 also the front between existing and the new
addition. States they tried to shape up the
21 back of the house by making the windows all
uniform sizes. Explains between the two bow
22 windows they added wood paneling. States they
added shutters all around the house around the
23 windows. Explains the other item requested was
the retaining wall at the back. States he
24 personally inspected the wall and submitted the
report to the Board. States his inspection of
25 the wall showed the overall structure of the
wall is sound with only minor problems that
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
will be taken care of during construction.
2 States there was a request for a picture of the
back of the house from different sides. Shows
4 Ms. Uhle: States the neighbor to the rear
brought up the issue with the retaining wall.
5 Asks engineer to summarize what the report says
regarding the retaining wall.
Mr. Adley: Reads report into the record.
7 States wall was found to be good and structural
integrity of the wall was sound at the time of
8 the inspection. States the typical condition
throughout the wall is there are a few loose
9 stones and missing mortar. States that will be
Ms. Uhle: Asks if that is something that could
11 be rectified as part of this approval.
12 Mr. Adley: States yes.
13 Mr. Cermele: States first stipulation is that
the structural wall will have to be repaired as
14 recommended by the engineer's comments. States
dead tree trunk should be removed so that wall
15 it's resting on could be repaired. Asks if
anyone from the public wishes to speak on this
17 Mr. Moses: Manfred Moses. States this is an
application for site plan and architectural
18 review and he has not seen the site plan.
19 Ms. Uhle: Explains the way the zoning law is
written architectural review is incorporated
20 into the architectural review process but since
they're only doing a second story addition
21 they're not effecting their existing site plan.
22 Mr. Moses: Feels this application is not ready
for approval until a site plan is provided.
Ms. Uhle: States they did provide a site plan
24 to the Planning Board. Explains because this
is the second time this application is being
25 presented to this Board most of those issues
were addressed at last month's public hearing.
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
States this is a continuation of the public
2 hearing from October 26th. States the site
plan issue along with the architectural review
3 issues were addressed at the last meeting.
4 Mr. Adley: Shows site plan.
5 Mr. Moses: States he appreciates the applicant
Mr. Pulaski: Makes a motion to close the
7 public hearing on Application 05-85.
8 Ms. Cascione: Seconds motion.
10 Mr. Pulaski: Refers to rear elevation.
Discusses bow windows on the rear elevation.
11 Discusses in fill between the two bow windows.
12 Mr. Adley: States the bow windows are no more
or less than twelve inches at the peak of the
13 window. Explains because there is a break
between the soldier brick line and the split
14 level it will not be possible to run that so to
break that brick soldier line he added the wood
15 paneling between the two windows.
16 Mr. Pulaski: Asks if it is a border.
17 Mr. Adley: States it's like a border.
18 Mr. Pulaski: Feels it has a certain
massiveness. Feels it doesn't blend that well.
19 Asks if it's going to be a painted wood.
20 Applicant: States yes.
21 Mr. Pulaski: Asks color of shutters.
22 Applicant: States green.
23 Mr. Cermele: States panels should be painted
the same color as the frame of the bow windows.
Ms. Cascione: States she likes the panel.
25 States the only condition would be correcting
1 EASTCHESTER PLANNING BOARD MEETING - 11/30/05
2 Mr. Adley: States the owner will correct the
retaining wall while he is doing the
3 construction. Explains it's minor repairs.
4 Mr. Pulaski: Makes a motion to approve
Application 05-85 per the plans with the
5 condition that the engineer's recommendation of
the repairs needed to the retaining wall get
6 performed and that the dead tree in
relationship to that wall get removed.