2 EASTCHESTER PLANNING BOARD MEETING
. . . . . . . . . . . . . . . . . . . . . . X
7 EASTCHESTER PLANNING BOARD MEETING
. . . . . . . . . . . . . . . . . . . . . . X
11 HELD AT: Eastchester Town Hall
12 Eastchester, New York 10709
14 BOARD MEMBERS IN ATTENDANCE:
15 Joseph Cermele, Member
16 Angela Cascione, Member
EASTCHESTER EMPLOYEES IN ATTENDANCE:
LOUIS REDA, Deputy Town Attorney
21 MARGARET UHLE, Director of Planning
JAY KING, Building Inspector
22 KERI OUELLETTE, Assistant Planner
24 DINA M. MORGAN, REPORTER
25 BRONXVILLE, NEW YORK 10708
1 EASTCHESTER PLANNING BOARD - 8/1/07
Mr. Pulaski: Calls meeting to order.
Mr. Pulaski: Explains this is a special
5 meeting for the Siwanoy Country Club
application. States there are only three board
6 members present so should there be any vote
taken all three have to be in agreement for it
7 to pass so the applicant is given the
opportunity to decide whether or not they want
9 Mr. Null: William Null, Cuddy & Feder.
Feels meeting will be helpful for informational
10 purposes to proceed and discuss where they are
status wise. States primary focus was drainage
11 issues in and around Siwanoy. States town
retained two consultants and we could hear from
12 them. Explains their expectation is not to
request any action but utilize this meeting to
13 keep updating each other.
14 Mr. Reda: Asks if they still wish to
proceed but they do not require any action.
Roll call conducted by Ms. Cascione:
Ms. Cascione: Present. States the
20 chairman and Mr. Bonnano will not be attending
Mr. Pulaski: States he would like to
22 make it known to the public that the town has
hired two engineers to look into this matter
23 and they are both present, Alan Pilch of Evans
Associates who is specifically reviewing the
24 Siwanoy application and Steve Grogg of Maclaren
Engineering. States they should hear from JMC
25 first as far as how they responded to the
1 EASTCHESTER PLANNING BOARD - 8/1/07
Mr. Lombardi: Dave Lombardi, John Meyer
3 Consulting. Discusses storm drainage.
4 Ms. Uhle: Asks if all the on-site
drainage will be directed to that open channel.
Mr. Lombardi: States yes, on-site
6 drainage from the project area which is the
parking lot, the pool areas and driveway.
Ms. Uhle: Asks if that was going into
8 the existing pipe and now it will not be going
Mr. Lombardi: States that is correct.
10 Shows existing drainage. Shows thirty-six inch
pipe on Crawford and eighteen inch pipe on
11 Archer Place. Explains the combined capacity
of three pipes is sixty-eight cubic feet per
12 second and thirty-six inch pipe that currently
comes through the site only has a hydraulic
13 capacity of fifty cubic feet per second. Shows
proposed plan. States the bypass they propose
14 down Crawford and across the eighteenth hole is
a forty-two inch plastic pipe which could
15 handle the combined capacity of the three
Ms. Uhle: Explains there are still some
17 outstanding issues that need to be resolved
before the board could approve this.
Mr. Lombardi: Explains this project is a
19 combination of redevelopment and new
development. Shows redevelopment. Shows new
20 development. Explains the entire project
including the parking area, new building and
21 pools the flows will be slightly less than
Mr. Null: Discusses easements. Explains
23 where there is an existing drainage line going
through their site there is no easement for the
24 town and they are willing to grant an easement
for the town with the opportunity to either
25 relocate or abandon it if there is an
1 EASTCHESTER PLANNING BOARD - 8/1/07
2 alternative method that the town comes up with
to drain. States the key component that
3 remains open is this drainage issue for the
area and is there something that Siwanoy can
4 accommodate on the property.
5 Mr. Pulaski: States there is a Maclaren
report that is studying the town.
Ms. Uhle: Explains they're evaluating
7 the drainage area that ultimately flows into
Ms. Uhle: States this is a good
9 opportunity for residents to ask questions.
Reviews what Siwanoy has done. Explains as a
10 result of the development and storm water
management plan they are meeting all the DEC
11 requirements and there is no net increase of
runoff and there was a slight decrease in the
12 flows. States in addition to that based on Mr.
Pilch's recommendation they have taken some of
13 that water out of that system as well because
they are going to be directing it to the open
14 drainage. Asks if there are any other things
that mitigate upstream conditions.
Mr. Null: States he doesn't believe
16 there is a need to mitigate upstream. States
they are looking to improve upstream. States
17 their obligation is to mitigate impacts
associated with their development.
Ms. Uhle: Explains what Siwanoy is
19 proposing and what they're doing is not
significantly resolving the problems upstream
20 and that is what Mr. Grogg is going to be
Mr. Grogg: Steven Grogg, Maclaren
22 Engineering. Explains they have been retained
by the town to do a drainage study of the
23 Crawford Avenue storm drain system which is the
subject of this development because the
24 thirty-six inch pipe passes through the country
club. States they have done field surveys so
25 they have good information on the existing
storm drain up to Crawford. Explains they are
1 EASTCHESTER PLANNING BOARD - 8/1/07
2 looking at the overall drainage basin. States
there is a lot of runoff that goes to that
3 storm drain that has resulted in a lot of the
problems that people have experienced. States
4 they are looking at the existing conditions and
coming up with alternatives to alleviate the
5 flooding problems that have occurred. Explains
ultimately any supplement or addition to the
6 storm drain system will ultimately need to
discharge to the golf course probably by the
8 Ms. Uhle: Asks Mr. Grogg to explain what
they are doing and how it relates to the
10 Mr. Grogg: Explains the town through the
DPW department is pursuing their own
11 investigation by videotaping some of the sewers
to determine if there is infiltration, cracked
12 pipes, looking for illegal connections, they're
doing smoke tests to determine if there are
13 illegal connections such as down spouts or
other things. Explains down at the end of
14 Adler Lane there was a sanitary manhole in a
low area, they have raised that manhole framing
15 grate by three or four feet so that when it
floods down there all that water doesn't go
16 into the manhole. States the town is being
very proactive with respect to the sanitary
17 sewers. Explains as you improve drainage
conditions so there is not flooding, ponding of
18 water which can back up into the sewers that
should also help that condition.
Mr. Pulaski: Asks if there is anyone
20 from the public that would like to speak.
21 Mr. Lively: Frank Lively, 52 Alder Lane.
Compliments Siwanoy on what they have done and
22 everybody else for the cooperative effort.
Asks if the mitigation plan as it relates to
23 the Siwanoy project addresses the issues or
concerns or questions that Mr. Pilch raised in
24 his report. Asks if the encapsulation of the
pipe on the property is something that is
25 mitigated by opening it up again. Asks if the
Maclaren report ties into or has any ability to
1 EASTCHESTER PLANNING BOARD - 8/1/07
2 make recommendations as it relates to the
Siwanoy proposal or is it something that's
4 Mr. Pulaski: Feels they're tied in
because they're all reporting to the planning
5 department and the planning department is tying
Mr. Pilch: Alan Pilch. Explains John
7 Meyer Consulting in their review did show that
their impact would be less at the design point
8 they selected which is where the existing pipe
discharges to the present channel on the
9 property. States there is a decrease and
Sitheir numbers are consistent and correct.
10 Explains they suggested taking all of the
drainage and remove it from the pipe entirely
11 so that what's going through Archer Place and
through the Siwanoy Country Club is just the
12 flows from the neighborhood. Explains Siwanoy
has done above and beyond what they have needed
13 to do. States when they extended the pipe
previously it reduced the capacity slightly in
14 the pipe. Explains by removing their flows
from that thirty-six inch pipe they actually
15 somewhat mitigate that impact in the first
place. States Steve Grogg and Maclaren should
16 review the entire drainage system to see
whether or not opening that up again would make
17 sense or just doing the bypass pipe. Explains
as it is right now there would be a lot of
18 disruption on the golf course to reopen that
and the benefit would be very small. Feels
19 it's better addressed inside the overall study
that Maclaren would be doing. States by
20 removing their flows from that pipe they
somewhat addressed the restriction of the
21 capacity of that pipe.
22 Ms. Uhle: Asks Mr. Pilch to address the
concern with regard to the bypass pipe and the
23 concept of this phase two construction.
24 Mr. Pilch: Shows squash court building.
Explains in order to construct the squash court
25 building John Meyer Consulting is proposing a
bypass pipe that would essentially go around
1 EASTCHESTER PLANNING BOARD - 8/1/07
2 the building and they would abandon the
thirty-six inch pipe that the squash court
3 would be constructed over. States he expressed
concerns with that bypass pipe. One is that
4 the bypass pipe would be essentially flat and a
flat pipe generally has a reduced capacity.
5 Second, the ninety degree bend in the pipe is
an opportunity for losses to occur in the
6 hydraulic capacity of the pipe. States he has
concerns with that. Explains they expressed
7 those concerns to Siwanoy. Explains that could
be addressed in a number of ways. One is they
8 could do a study and review what the capacity
of that pipe would be with that bypass, they
9 could reconfigure the architecture of that
building to avoid constructing it over the
10 existing thirty-six inch pipe or the bypass
pipe might negate any of the concerns with that
12 Ms. Uhle: States Siwanoy has indicated
they're not planning to construct that portion
13 of the building at this time so that would be a
phase two construction. Explains a condition
14 of approval could be that they come back with a
separate application at that time and the
15 drainage issues could be discussed separately
with regard to that bypass because that could
16 be effected by whatever design improvements are
proposed by Mr. Grogg. Explains Mr. Pilch said
17 that is not acceptable, Siwanoy said they're
not planning to construct that at this point
18 under any circumstances so they would have to
re-evaluate that and conditions may be
19 different at that time when they come back for
that phase two construction, if they come back.